Thursday, July 29, 2021

Welcome to Liz Larvor, new Trustee and Secretary

 


Welcome to Liz Larvor, new Trustee and Secretary


I’ve been a member at EARM since 2016 now, I’ve always had an interest in helping the organisation in any way that I can. From photography, to getting my hands filthy on the odd occasion in the resto shed. In more recent years I’ve assisted the board of trustees with administrative tasks and acting as N7 trustee liaison as part of the restoration project. Using my background in audit risk management I’ve challenged the way we do things and I’d like to think that I’ve bought about some changes





At the May trustees meeting I was co-opted in as trustee to take over from Mike Stanbury as Museum Secretary, along with taking on some of the marketing responsibilities from Mark Cornell. I look forward to seeing where the museum goes in the future.


As Liz takes on new responsibilities, the long service given by Mike Stanbury must be recorded. To record Board decisions at meetings is the prime responsibility of a secretary, these must now number in the hundreds over decades in the past. At times it may be pleasurable to record a year of good progress, but at other times more challenging replies have been composed for AGMs and other bodies needing annual reports. Less welcome would-be official notifications to the museum of a legal kind from authorities, as Secretary these have received and responded to. 

Mike looking back is particularly pleased to receive acknowledgement from the former Railway Inspectorate, on the quality of his response when an Exemption to railway safety case working was being progressed, these apply to smaller preserved railways.  Mike has served the museum admirably and his retirement from these responsibilities goes with thanks, as it truly well deserved, from the museum membership.





Restoration of the N7 locomotive continues.

 


Restoration of the N7 locomotive continues.

On Wednesday 30th June, the boiler was transported away to Heritage Boiler Steam Services Ltd of Huyton Liverpool for ongoing examination and eventual overhaul. It is currently funded to continue exploratory works using Restricted funds provided for this purpose in a previously received large bequest.

In a contract between the company and museum, there is reportedly a (editors’ terminology) “stop and wait provision” should funds be near exhaustion then work can stop. This is important, in this way there is no full liability to complete work in one continuous operation, thus avoid incurring further expenditure not covered by fundraising.

In this way further fundraising can proceed better knowing of its condition, progress and therefore a refined estimate of costs. All boiler work comes with a degree of uncertainty, boilers vary in their condition and how they respond to “treatment”. Our Chappel N7 locomotive team have done the necessary preparation works, so the success of this project dwells principally on the contractor and fundraising to perform well. A new 52-page publication “69621 – Star of the Jazz”, is on sale from the VRC. It details the locomotive class history, details of restoration of the locomotive and its current condition as has been sent away for specialist boiler attention.

A number of other locomotive restoration projects are also being progressed by the company, a new website exists to show all current projects and the skills employed on their web site.

https://heritageboilersteamservices.co.uk/projects





A short video introduces you to the team at Heritage Boilers who will be working on the boiler.

H B Staff video


Liz Larvor, has set up a web promoted fundraising appeal that has now been launched on the museum’s. Like others before, the appeal for funds splits the task into smaller manageable pieces. In this way £100K can potentially be raised through smaller individual donations.

Currently advertised opportunities to sponsor a ‘Copper Stay’ for £35 (800 available), a ‘Crown Stay’ for £50 (100 available), a ‘Smoke Tube’ for £60 (134 available) and a ‘Flue Tube’ for £680 of which 18 are available, inclusive of a complimentary ‘Half Day Driver Experience’ course on the locomotive. Alternatively, a “General N7 Donation” option is given, of any amount can be made.

Monies can be collected in a number of ways, directly from the museum’s website   posting a cheque to the museum or by arrangement a bank transfer.

N7 Restoration Appeal

This appeal is now been circulated to press and web news outlets. Regular updates on the restoration progress is to be submitted to the Board of Trustees, when possible copied in Chappel News too.




Museum department news July 2021

 


Museum department news July 2021

These notes are now compiled by a combination of Head of Department minutes compiled by Colin Burwood and social media posts (as this form of communication is becoming more dominant). It is not possible here to record all actions on site, so day to day reporting is best seen on the “WhatsApp” postings, these are seen by over 60 people. 

Estates & Plant

Norman Tenner and Robert Page are leading equipment training about strimmer use. Weed spraying equipment has been purchased and adapted to fit the tractor. Initially two people will be trained in how to use it. 

Richard Gourlay assisted by Aimee, Chelsea, Adam and Matthew have externally painted the south side of Gresley coach alongside Platform 6. It is known that the coach is to remain on site, what is not yet known its internal display space will be re-equipped with.

Proceeds from a second container of scrap metal raised a useful £716. A ride-on mower is now fully operational proving it’s worth with grass cutting in small areas and carrying equipment around the site using a trailer donated by Martin Gibbons.

For those with an interest in environmental items, a new “Heritage Rail Ecology” Facebook group has been set up, with several EARM members contributing. To help manage cuttings made from pruning and weeding activities around site, new composting bins have been provided. 

Team Wednesday 

All credit to the team, with not one but two completed projects! TW are happily back to near full strength and they have proven themselves ready for new challenges. Being quite expert at removing and re-purposing buildings, the former B1 building is now stripped ready for removal. This is required to accommodate the new Exhibition Hall (CN82 /Aug2020). Taken into stock is a large quantity of timber and insulation material. 

Completion of their second project, was re-roofing and repairs to the infrastructure workshop (PW and S&T), formerly MiniRail loco shed. 

TW are now starting their next big project, to use what can be salvaged from the Luggage Composite coach of 1888, to be the face of a Viaduct pub extension. Tim Rice has prepared a virtual illustration of what may be possible. It is expected to have a "new build" back, and have the facade at best endeavours with what material is salvaged.


 


Carriages & Wagon

Work on the BCK is progressing and is expected to be ready for Thomas events at the end of August. A brake problem on the BS has been rectified which was difficult to isolate. Replacement flooring is being placed in the HiBar wagon, which is destined to be a wood store outside. 

Permanent Way 

A plan to tackle out of gauge track in the yard area is being put together by Andrew Cullum and others. This will involve significant excavation and replacing previously assembled track panels. Add to your diary November for major track-gang works - subject to confirmation from Operations.


Signalling

All equipment remains operational, with maintenance tasks and inspections being completed as and when due, the most notable being North Box, which has a full frame inspection and test.

Miniature railway 

A third and fourth new passenger coaches have been delivered, two borrowed from Barnards have now returned. Entrance gates for the station installed to regulate entry and exit of customers. Training and assessing of additional staff for driving and station duties is progressing.



Exhibition Hall works.

 


Exhibition Hall works


Preparatory works are in progress, requiring diversion of services, and Team Wednesday stripping down the former B1 building to its steel frame. A crane contractor will be called upon to move the frames southwards lower into the engineering field, to establish a covered place to store plant and machinery.



All drawings for the Exhibition Shed foundations, levels and steel work have been approved, the Council have passed a conditions document. Allan Robinson is progressing through Building Regulations with the architect.

Foundation work is planned  to start in August, for construction it is necessary to soon block off the current staff car park for which new barrier signage is to be provided.

Contractors are expected to erect the steel frame and roofing in late October. Internal fit-out works are yet to be planned and progressed by the museum, as finance and labour permits. 


Events Feedback ( late May to July 2021)

 



Events Feedback ( late May to July 2021)

May saw the return of the Transport Event taking place over the Spring Bank holiday weekend, this event is now well established with a significant input by the Cornell family.  Andrea was kept busy keeping contact with the various clubs. Admission figures were good, with 220 visitors in Saturday, 270 Sunday and 348 on the Bank holiday.

A very successful “Home Fleet Diesel Gala” took place on Sunday 18th July 2021. It featured principally the launch into public service Waggon und Maschinenbau (W&M) Railbus E79963

Pre-event Facebook publicity was prepared for the event by Neil Temlett , Craig Greenslade is helping us the museum with video promotions

https://www.facebook.com/earailwaymuseum


A post recently added also included a non-railway story, the rescue of a cat outside the museum, its a lively 
forum which  6,648 people follow !  





A comprehensive booklet was produced for the event by Jack Plumb, a portion of which is re-produced above, highlighting the fleet of six and during the day its more complex movements. Over 170 people enjoyed a ride in the Railbus that worked perfectly. It’s trials and tribulations during restoration have featured many times in Stour Valley Steam, within editions 152, 156, 164 and 168.

During its first public outing it was an extremely hot day and driving at the control desk gave new meaning to the term “hot desking”. It is yet to be found out what it's like in colder weather; as it is a four-wheeled vehicle a greater level of care will have to be taken during times of poor weather with reduced rail adhesion.





Museum Opening - post lockdown arrangements

 


Museum Opening - post lockdown arrangements


The Museum 

Is now open on Wednesdays and the weekends over the summer, with events already planned. Consideration is being given to opening on further days during August. 


Darren Johnson has produced 1000 advertising flyers, sponsored by Martin Gibbons. Members are distributing at hotels, B&Bs and, caravan sites in the area, further flyer leaflets will be produced when events are confirmed. Volunteers will need to exercise their own judgement regarding mask wearing and social distancing whilst working on site.


Days out with Thomas

Will be held Saturday 28th to Monday 30th August; after a significant amount of effort by the engineering teams to get locomotives and carriages with fit to run confirmation.


Braintree & Halstead Model Railway Club 

Are now re-opening for club nights, and their display room after having to stay shut for over 15 months. For the diesel gala their Lymswold display featured a W&M Railbus and class 04, adding some interest for children. 

Small Trains Day will be held on the Sunday10th October.  [ not the 18th October ] 

News on current projects is posted on a separate web site Braintree & Halstead MRC


EARM promoted Beer Festival from 7th to 11th September

Brendan Sothcott reports it has been planned to hold a smaller. Currently there are sadly still uncertainties, which results in a 75% chance of operating. Restrictions will apply, the main ones are:  Admission by advanced ticket sale only, two sessions are run daily (except Tuesday), entry from 11:00 to 17:30 and second session 17:30 to 23:00. Beers served in Goods Shed – the consumption of beers has to be outside.

Beer Choice will be reduced to about 100 beers and many ciders.  A smaller range of food offerings, Vegetarian and Vegan options are offered, but these do sell out early. There will be no bands playing or public camping, nor can children and animals be welcomed this time around.

 

 Please keep browsing for updates: chappelbeerfestival.org.uk